Previous Page  4-5 / 8 Next Page
Information
Show Menu
Previous Page 4-5 / 8 Next Page
Page Background

FEATURED PROJECT

A

laska derives its wealth from its crude oil and nat-

ural gas deposits, and most of them are located in

the Cook Inlet. Exploitation started in early 1960s,

but there is still a strong potential for development.

In March 2015 MV Svenja was chartered for the instal-

lation of the development platform within the Kitchen

Lights Unit #3, a petroleum exploitation area of Deutsche

Oel & Gas AG. Covering 337 square kilometers, this is

the largest development region in the Cook Inlet.

The development platform consists of three main

parts: The

Monopod

, a 45 m high steel base which,

ultimately, will bear the load of the whole construction. It

is stabilized by the

King Pile

, which works as a central

pole, driven into the seabed. The other two main parts

are the

Topside

and the

Helideck

.

For this scope of work MV Svenja required an exten-

sive and technically challenging and time-constrained

mobilization in Singapore. Extra living quarters were

needed for the

60 supporting team members

neces-

sary to complete the project working and living on board

for almost five months.

Because of the extremely strong surface sea cur-

rents at the installation site, a special mooring arrange-

ment was designed for the vessel which comprised of

ten pre-installed anchors

strategically located on the

seabed. The shipboard component of this arrangement

THE

BIGGEST

MARINE

ASSET

MV Svenja at the KLU Project

ADDITIONAL GALLEY, MESSROOM

& LIVING QUARTERS FOR

60 TEAM MEMBERS

SPECIAL MOORING WINCHES

comprised

10 winches

and wires which were connected

to the pre-laid arrangement. This configuration provided

safe and secure mooring along with precise positioning

of the vessel despite the strong tidal currents.

Once the MV Svenja was secured within the moor-

ing pattern, the first job was to drive the King Pile to the

required depth. This was achieved with the use of a large

hydro hammer

. The King Pile not only holds the Mono-

pod securely on the seabed but it also acts as a guide

ensuring exact positioning of the Monopod.

With the King Pile in place, the Monopod was trans-

ported to MV Svenja by a barge and then lifted onto

her deck for additional preparations. Subsequently the

two 1000 t cranes of MV Svenja lowered the

Monopod,

which weighs 1100 t,

accurately down to the seabed.

Once the Monopod was landed and the cranes freed,

eight additional piles

were driven through guides on

the Monopod securing it to the seabed.

The Monopod was installed successfully on June 2,

four days prior to planning. Next steps will now be the

installation of the Topside and Helideck.

D

To be continued in the next NEWSBREEZE issue …

“MV Svenja is the biggest marine

asset which we have available to us

at this time. With her two cranes we

were able to successfully install the

monopod on the seabed.”

Oliver Arnold, FURIE,

project manager of KLU

5

4