Previous Page  5 / 20 Next Page
Information
Show Menu
Previous Page 5 / 20 Next Page
Page Background

KLU / PHASE 2

W

hat happened so far:

MV Svenja was chartered for the installation of the

development platform of the Kitchen Lights Unit #3, a

petroleum exploitation area in Alaska operated by Deutsche Oel

& Gas. Covering 337 square kilometers, it is the largest exploita-

tion area in the Cook Inlet.

Arriving on site in late spring, MV Svenja was positioned in a

special mooring spread, provided by ten pre-installed anchors

on the seabed corresponding with ten additional winches on-

board. Precisely moored, MV Svenja served as a fixed offshore

project platform despite the strong tidal currents. In June and

July, the subsea structures for the exploitation platform, consist-

ing of a Monopod of 1100 tons and a transition piece, have been

installed successfully – even four days prior to planning.

Completing the project

In early August the Topside, measuring 33 × 30 × 27 metres, was

installed onto the Monopod with a 700 tons single hook lift.

“The

Topside installation was an extremely tight lift with very small

tolerances. It could only be carried out during high tide with

an installation window of about four hours”

, explained Captain

Rüdiger Bauer.

“For this reason, careful planning and exact

execution was necessary for a successful installation”,

he went

on. Within two hours including the lift from the barge, the Topside

was placed on the Monopod.

This step was followed by the installation of the Helideck

measuring 16 × 15 × 6 metres and weighing 40 tons. Although

this part of the installation was carried out by a rather simple lift,

it still demanded proper planning due to the lifting height and

the placement of the center of gravity. The installation went as

per schedule. Both SAL and its client Crowley were absolutely

satisfied with the course of the installation.

“SAL was our pri-

mary heavy lift contractor for a highly technical and environ-

mentally challenging installation of an offshore platform over a

subsea gas well conductor. SAL’s technical skills, their vessel

MV Svenja and the team’s operational experience led to a very

successful installation”,

states Michael Johnson, Statement

Project Manager of Crowley.

Completing the installation of the Helideck and Topside, an

essential milestone towards the completion of the infrastructure

in the Kitchen Lights Unit #3 has been reached. From end of

2015 on, the first natural gas shall be produced from the Kitchen

Lights Unit.

Holger Krenz, responsible Project Manager at SAL Heavy

Lift, also expresses his great satisfaction with the project:

“SAL

is very pleased to have been chosen to undertake the highly

technical and complex installation of the offshore platform for

our client Crowley. In this project SAL has been able to make

excellent use of its specialist knowledge and capabilities to

the advantage of our client, Crowley, with the result that a safe

and successful project was delivered.”

MV Svenja has returned for demobilization – ready for the

next challenge.

D

“SAL’s technical skills and operational

experience led to a very successful installation.”

Michael Johnson, CROWLEY, Project Manager KLU

5