OUR SOLUTIONS




            PYRENEES PROJECT

          Location
          Malus Channel in Dampier Archipelago, W. Australia
          Client-provided items (CPI)
          Spider buoy (part of an FPSO mooring system)
          Weight
          800 mtons

          Scope of work
          •  Open hatch transport
          •  Offshore load-out
          Specials
          Challenging size of the spider buoy:
          only 10 cm space left on each side of the vessel’s hold                                                       POHOKURA PROJECT
     OIL & GAS                                                                                                       Location


                                                                                                                     Taranaki Bassin, New Plymouth, New Zealand
                                                                                                                     Client-provided items (CPI)
                                                                                                                     Steel jacket and offshore wellhead platform
                                                                                                                     Weight
                                                                                                                     420 t (steel jacket)
                                                                                                                     Dimensions
                                                                                                                     56 m length (steel jacket)

                                                                                                                     Scope of work
                                                                                                                     Transport
                                                                                                                     Specials
                                                                                                                     •  SAL – in cooperation with their client Technip –
                                                                                                                       engineered a method to rotate the steel jacket during
                                                                                                                       the lifting process, keeping the structure 1 m off the
                                                                                                                       ground at all times
                                                                                                                     •  In a world first, the complex structure was turned from
                                                                                                                       a horizontal to a vertical position, being placed into the
                                                                                                                       vessel, where it extended 42 m above the hatch
                                                                                                                     •  For the offshore uploading of the structure,
                                                                                                                       MV Annegret moored just 4 m from the installation
                                                                                                                       rig up which lowered the jacket to the ocean floor