OUR SOLUTIONS
PYRENEES PROJECT
Location
Malus Channel in Dampier Archipelago, W. Australia
Client-provided items (CPI)
Spider buoy (part of an FPSO mooring system)
Weight
800 mtons
Scope of work
• Open hatch transport
• Offshore load-out
Specials
Challenging size of the spider buoy:
only 10 cm space left on each side of the vessel’s hold POHOKURA PROJECT
OIL & GAS Location
Taranaki Bassin, New Plymouth, New Zealand
Client-provided items (CPI)
Steel jacket and offshore wellhead platform
Weight
420 t (steel jacket)
Dimensions
56 m length (steel jacket)
Scope of work
Transport
Specials
• SAL – in cooperation with their client Technip –
engineered a method to rotate the steel jacket during
the lifting process, keeping the structure 1 m off the
ground at all times
• In a world first, the complex structure was turned from
a horizontal to a vertical position, being placed into the
vessel, where it extended 42 m above the hatch
• For the offshore uploading of the structure,
MV Annegret moored just 4 m from the installation
rig up which lowered the jacket to the ocean floor