OUR SOLUTIONS






            MA-D6

          Location
          Offshore Kakinada, India
          Client-provided items (CPI)
          Nine suction anchor piles
          One manifold installation suction pile
          One production manifold
          One STP buoy
          Maximum weight
          330 t manifold
          150 t suction piles
          Vessel modifications and deck equipment
          The main deck equipment item was a 330 t linear winch
     OIL & GAS  Scope of work
          and over-boarding sheave.

          •  Transportation to site of the CPI
          •  Over-boarding of the subsea items followed by
           lowering to cross-haul depth
          •  Over-boarding of the STP buoy